We build projects that last

Our Projects

Thibodaux Regional Cancer Center

This project was finished in 2019 when the cancer center was opened. We completed Stuctured Cabling for all voice/data, CCTV cameras, wireless access points, fiber optic cabling, cable tray and IT room build-outs.
 

tribexterior.png
Delgado Nursing + Allied Health Building

 We started this project in Q3 of 2022 and completed it in Q2 of 2023. Our primary focus was the entire new facility, which was a 7-story building. We completed Stuctured Cabling for all voice/data, CCTV cameras, Access Control, wireless access points, fiber optic cabling, cable tray and IT room build-outs.

230419 1_1.jpeg
World War II Museum Parade Grounds

The project began at the start of 2021 and ended in Q3 of 2022. At the museum, we installed the fiber optic and DMX cabling that controls all of the LED lighting on the museum.

3Q9A2151-960x700-ar.jpeg
LCMC's East Jefferson General Hospital Renovation

We began this project in Q2 of 2023 and the project is still currently ongoing. We started this project to assist with the entire facility renovation. We completed Stuctured Cabling for all voice/data, Access Control, CCTV cameras, wireless access points, fiber optic cabling, cable tray and IT room build-outs.

entrance1-east-jefferson-general-hospital-behavioral-health-metairie-la-70006.jpeg
Patrick F. Taylor Multipurpose Center

We started this project in Q2 of 2021 and ended in Q4 of 2021. We provided structured cabling for all data and wireless access points and installation of wireless access points.

460601911_7812551215515931_2126482269740900555_n.jpeg
Thibodaux Regional Medical Center Sports Facility

We began this project at the start of Q4 of 2021 and ended in Q3 of 2022. Our primary focus was the Sports Facility and the Wellness Center, where we installed underground fiber optic and CAT 6 cable, we also installed a new cameras system for the new Sports Complex.

crop.webp
New Orleans Career Center

This project was started in Q4 of 2021 and completed in Q2 of 2023. We provided Stuctured Cabling for all voice/data, CCTV cameras, wireless access points, fiber optic cabling, cable tray and IT room build-outs.

images (1).jpeg
Tulane University Bruff Hall

We started this project in Q2 of 2022 and ended in Q2 of 2023. We focused on the entire facility, new construction 400 room residential building. We provided stuctured Cabling for all voice/data, CCTV cameras, Access Control, wireless access points, fiber optic cabling, cable tray and IT room build-outs.

IMGP9528.jpeg